Bayfront Health Spring Hill Labor and Delivery Renovation

Bayfront Health Spring Hill Construction Project in Florida

Project description

The nearly 23,000SF renovation was a four phase project that spanned the course of eight months.  The first floor L&D Unit, 2nd Floor MCU, waiting rooms and several staff areas including nurse stations were completely revamped including new flooring, fresh paint, new casework, updated LED light fixtures and more.  The renovation has provided patients with additional comfort and a modern environment.

LOCATION
Spring Hill, FL

PROJECT DURATION
8 months

PROJECT VALUE
Approx $1.5 million

CONTRACT TYPE
CM at Risk (GMP)

SERVICES PROVIDED
Preconstruction Services
Construction Estimates
Constructability Reviews
Coordination Meetings
Value Engineering
Subcontractor Pre-Qualification
Existing Conditions Verification
Phasing Coordination
Construction Services
Budget Management
Schedule Management
Progress Meetings
Change Order Meetings
Quality Control
Coordination with Local Governing Boards

ARCHITECT CONTACT
Jim Harris
TM Partners
941-388-5340

CLIENT CONTACT
Joe Hall
Bayfront Health Spring Hill
352-688-8200