Van Dyke Medical Office Building

Van Dyke Medical Office Building Construction Project in Clearwater, FL

Project Description

The project consisted of two poured in place concrete structures, both two-stories and 20,000 sq. ft. Both buildings were designed to be extended to two more stories. The pods were built out to include diagnostics, CAT scans, mamography and physician offices. The site development including all underground utilities, power, storm retainage, entrances, parking and landscaping were all part of the project’s scope.

PROJECT DURATION
10 months

PROJECT VALUE
$9.6 million

CONTRACT TYPE
General Contractor

SERVICES PROVIDED
Scheduling
Change Order Management
Progress Meetings
Quality Control
Coordination Trades

ARCHITECT CONTACT
Michael Smith
Rañon & Partners, Inc. Architects 515 W Bay Street
Tampa, FL 33606 813.253.3465

CLIENT CONTACT
Deb Bartley, Construction Manager
Morton Plant Healthcare
1233 South Fort Harrison Healthcare
Clearwater, Florida 33756 727.734.6061