Morton Plant – Dunedin Surgery Expansion and Renovation

Morton Plant - Dunedin Surgery Expansion Construction Project in Florida

Product Description

The scope involved a six-phase project consisting of a 4,100 square foot addition and 35,400 square foot renovation of former the Intensive Care and Critical Care Unit, which was transformed into new Operating Suites with state-of-the-art equipment.

Project Unique Characteristics:

• Extremely critical phasing because of the need to have original number of Operating Suites operational and accessible while transforming the existing space.

• Brought the new Operating Suites into service before taking others out of service, while ensuring the safety of patients and maintaining the capability to perform needed surgeries.

OTHER MORTON PLANT MEASE HEALTHCARE PROJECTS COMPLETED SINCE 1992:

• Cafeteria Renovation, Clearwater
• Eastlake Ambulatory Care Center
• B4 ICU Renovation
• Witt Building Renovation – 2-7
• Trinity Ambulatory Center
• Day Surgery, Clearwater
• B2 ICU Renovation
• Inpatient Cardiac Cath Lab, Countryside
• Radiation, Endoscopy, & Emergency Departments & Renovation Expansion, Dunedin
• Witt Ground Floor Renovation
• Fire Sprinkler Upgrade, Dunedin
• Fully Sprinklered Alteration, Clearwater
• Emergency Room Renovation, North Bay
• Headwall Renovation, Dunedin
• Witt Building Kitchen Equipment Replacement
• Kilgore Building Renovations
• Laminar Flow, OR #9
• Renovate 2nd Floor, Dunedin Hospital
• Renovate 3rd Floor, Dunedin Hospital
• EKG Renovation, Dunedin Hospital
• MAB Renovation, Dunedin Hospital
• MRI/Cardiology Renovation, Countryside Hospital
• ICU/CCU Renovation, Dunedin Hospital
• Third Floor Renovation, Countryside Hospital
• Surgery Addition/Renovation, Dunedin Hospital

PROJECT DURATION
3 years

PROJECT VALUE
$8.3 million

CONTRACT TYPE
CM at Risk (GMP)

SERVICES PROVIDED
Pre-Construction Services
Construction Estimates
Constructability Reviews
Coordination Meetings
Construction Cash Flow Analysis
Value Engineering
Subcontractor Pre-Qualification
Existing Conditions Verification
Phasing Planning
Construction Services
Budget Management
Schedule Management
Progress Meetings
Change Order Control
Infection Control Measures
Ongoing Value Engineering
Coordination of Medical Equipment
Quality Control
Coordination with Local Governing Bodies

ARCHITECT CONTACT
Wayne Vert, TRO
Jung/Brannen
Sarasota, FL 34236
941.366.9486

CLIENT CONTRACT
Deborah Bartley
Morton Plant Mease Health Care
Clearwater, FL 33756
727.734.6061