Wehr Constructors provided construction management, including pre-construction services for the vertical expansion at the Medical Center at Bowling Green, Kentucky. The project includes the addition of 2 new floors totaling 49,000 square feet on the existing hospital with some minor renovation in the existing building below. A new emergency egress stairwell was also required.

The new third floor included 24 beds with a new orthopedic unit and physical therapy area. Fourth floor construction includes 24 beds and a new intermediate surgical care unit with a specialized recovery area.

Wehr Constructors has been developing various projects with the Medical Center at Bowling Green since 1982.

Project Duration:
2008-August 2010

Project Value:
$17 Million

Contract Type:
CM at Risk (GMP)

Services Provided:
Pre-Construction Services
Construction Estimates
Master Schedule Preparation
Constructability Reviews
Construction Cash Flow Analysis
Coordination Meetings
Value Engineering
Subcontractor Pre-Qualification
Existing Conditions Verification
Construction Services
Budget Management
Schedule Management
Progress Meetings
Infection Control Measures
Change Order Control
Ongoing Value Engineering
Progress Meetings
Coordination of Medical Equipment
Quality Control
Coordination with Local Governing Bodies

Architect Contact:
Paul Edwards
Stengel-Hill Architecture
Louisville, KY
Phone 502.893.1875

Client Contact:
Jean Cherry, CEO
Commonwealth Health
Bowling Green, KY
Phone 270.745.1500