Louisville Deaf Oral School

Louisville Deaf Oral School Construction Project in Kentucky

PROJECT DESCRIPTION

This new addition and renovation lasted 13 months and involved the existing Lousville Deaf Oral School in Old Louisville. Wehr Constructors served as CM at risk for this new multi-story school facility that includes 12 classrooms, divided into two separate pods. Shared spaces including the library, music room, art room and a cafeteria/multipurpose room bring students together on campus.

PROJECT DURATION
January 2001

PROJECT VALUE
$2.1 Million

CONTRACT TYPE
CM at Risk (GMP)

SERVICES PROVIDED
Pre-Construction Services
Construction Estimates
Constructability Reviews
Coordination Meetings
Construction Cash Flow Analysis
Value Engineering
Subcontractor Pre-Qualification
Existing Conditions
Verification Phasing Planning
Construction Services
Budget Management
Schedule Management
Progress Meetings
Change Order Control
Ongoing Value Engineering
Quality Control Coordination with
Local Governing Bodies

ARCHITECT CONTACT
H. Carleton Godsey III
Godsey Associates Architects
Louisville, KY
502.583.6611

CLIENT CONTACT
Mona McCubbin
Louisville Deaf Oral School
Louisville, KY
502.515.3320